Expert Guide
Babu
Planning & Costing

Labor Productivity & Daily Output

Quality Inspector
Kaka

Find required labor for specific tasks.

📐 Formula & Method

Workers = Total Work / (Output per day × Time in days).

Workers = Work / (Productivity × Days)

📋 Worked Example

100 m² plastering in 5 days:
• Daily Output needed = 20 m²/day
• Masons = 20 / 8 = 2.5 (Use 3 masons)

❓ Frequently Asked Questions

A Mason (Mistri) is a skilled worker who leads the task, while a Helper (Mazdoor) provides manual labor like mixing and carrying materials.